WCS will repurpose the existing Transportation Department administrative space into additional operating space for parts storage, freeing up bay space that is currently being used for storage. Additionally, a one-story, 4,600 +/- SF building will be constructed at the northwestern end of the existing Transportation Building for administrative and office space.
Location:
1777 West Main Street Franklin, TN 37064
Key Dates:
Bids were opened on November 3, 2023 and a contract was awarded to Fellowship Construction, Inc.
The Notice to Proceed with Construction was issued on February 19, 2024.
Substantial completion is expected to be completed by March 2025.